Client Duration Key Fact Valve
VITAL Energi 96 Weeks Installation, Coordination and matching existing flue facade -

A construction project in a very tight and busy area of the hospital which meant a well organised and devoted site team.

The CHP flue installation had to be routed adjacent to the existing flues and tie in with the existing façade design which required some cleaver engineering and a lot of site fabrication skills.

Enabling Works

Gas Installation preparation for main works

Low & Medium temperature hot water shutdowns

Extensive civil works building new sharp, clean & dirty linen stores and a waste storage facility, this included bases, structures, cladding and all associated services.

Key Deliverables

Gas Installation

Low & medium temperature hot water connections to existing Energy Centre systems

Chimney & interconnecting flues

LV panel, related electrical cabling and SCADA system

3.3 MW CHP connections, complete with ancillary equipment including dry air coolers & associated platforms

Connection, commissioning and intergration of new low & medium temperature plate heat exchangers

All civil engineering works

Strategic Elements

Liasing with the Hospitals Estate Department and issuing specifc project licence park information

Management and organising a very complex scaffold design & flue installation

Successes

The PIMS teams approach to working along side the Hospitals back of house

Another project effectively completed with VITAL Energi