Client | Duration | Key Fact | Valve |
---|---|---|---|
VITAL Energi | 96 Weeks | Installation, Coordination and matching existing flue facade | - |
A construction project in a very tight and busy area of the hospital which meant a well organised and devoted site team.
The CHP flue installation had to be routed adjacent to the existing flues and tie in with the existing façade design which required some cleaver engineering and a lot of site fabrication skills.
Enabling Works
Gas Installation preparation for main works
Low & Medium temperature hot water shutdowns
Extensive civil works building new sharp, clean & dirty linen stores and a waste storage facility, this included bases, structures, cladding and all associated services.
Key Deliverables
Gas Installation
Low & medium temperature hot water connections to existing Energy Centre systems
Chimney & interconnecting flues
LV panel, related electrical cabling and SCADA system
3.3 MW CHP connections, complete with ancillary equipment including dry air coolers & associated platforms
Connection, commissioning and intergration of new low & medium temperature plate heat exchangers
All civil engineering works
Strategic Elements
Liasing with the Hospitals Estate Department and issuing specifc project licence park information
Management and organising a very complex scaffold design & flue installation
Successes
The PIMS teams approach to working along side the Hospitals back of house
Another project effectively completed with VITAL Energi