Client | Duration | Key Fact | Valve |
---|---|---|---|
VITAL ENERGI | 96 Weeks | Boiler Installation Sequence | £ 2,600,000 |
A project working with VITAL Energi which included installing a services highway at the rear of the Energy centre which enabled us to coordinate all boiler / electrical and CHP services together.
Enabling Works
Phased removal and disposal of 4 off steam boilers, their flues, control panels and 2 off economisers.
Removal and disposal of steam header.
Removal and disposal of high level redundant steelwork, walkways and access ladder.
Removal of redundant piped services and blow down vessel.
Design, Installation, Connection and Commissioning
Installation of 2 No. 7 Tonne Steam Boilers
Installation of 7.85 Tonne Combination Steam Boiler
CHP Unit associated plant
2.0m x 3.0m x 2.0m high mild steel Hotwell
Steam Header and distribution system
Supply, assemble and commissioning of water treatment plant
Installation of a feed water system from the new hot well to all steam boilers including spill back system
Raw and treated water pipework
Installation of blow down system
Installation of new steam header, dirt pockets and trap sets including
Condensate system modifications
Gas system modifications
Installation of new fuel oil supply system from the inlet of the new pump
LTHW Flow & Return distribution to dispersed plantrooms complete with prefabricated Plate Heat Exchanger skids
Strategic Elements
Exciting strategy for the sequence of plant installation to guarentee the Hospital heat & power.
Installing a large Steam Header 7.5M long.
Successes
Prefabricated Plate Heat Exchangers commissioned and wired ready for SCADA connection in our work shop.
Project delivered on time and achieving 95% customer satisfaction.