Lister Hospital Energy Centre Modifications

Client Duration Key Fact Valve
DALKIA 11 Months Phased Boiler Replacement £ 1,100,000

The project involved the phased replacement of 5 existing steam boilers, the installation of 3 new boilers and a 1.4MW gas fired CHP engine.

Full service to the hospital was always required during the installation.

Key Deliverables

Design, Construction, Installation and Commissioning of two new hotwell tanks inclusive of structural steel support and access platform.

Phased removal and installation of 3 new steam boilers inclusive of all contract lifts.

Installation of a new 1.4MW CHP engine including LTHW network and 4 heat recovery stations within various hospital plantrooms.

Design, Supply, Installation and Commissioning of 4 new steam to DHW generators in a live plantroom including the phased removal of 6 x existing storage calorifiers.

Design of the layout inside the boiler house to facilitate safe working operation including integration of the engine, boilers, and ancillary equipment.

Strategic Elements

The requirement to maintain hospital services at all time was critical. 

Successes

Close liaison the client during the contract enabling all the required system shutdowns.

Process Installations were successful in completing the project on time.